Can someone help me on this question please:

If the objective function of a company using linear programming is 12M + 8N=Y and the constraints intersecting at the optimum point are as follows:

Material: 4M+2N < 240
Labour: 3M+2N < 190

What will be the shadow price of labour?

April 21st 2018 AN ACCA USER 270 Points
...