Can someone help me on this question please:
If the objective function of a company using linear programming is 12M + 8N=Y and the constraints intersecting at the optimum point are as follows:
Material: 4M+2N < 240 Labour: 3M+2N < 190
What will be the shadow price of labour?
Shadow price is 4